Long-term Major Water Supply Project Milestone Commitments

The following milestone commitments are agreed to for the large water supply project:

  • Project description to PSC--January 15, 2007

  • Preliminary conceptual design--Sept. 30, 2007 (facility/site layout, plant hydraulic gradient, process description, design basis)

  • Submit DEIS and all required environmental permit applications--Sept. 30, 2008

  • Complete pilot plant studies, if required--Dec. 31, 2009

  • Obtain environmental permits--Sept. 30, 2010

  • Complete 50% design--Sept. 30, 2011

  • Begin construction--May 31, 2013

  • In-service--Dec. 31, 2015

    This calendar for providing service is taken from United Water PSC Agreement 10/06.